SHAVKAT MIRZIYOYEV Year of ensuring human interests and development of the mahalla Year of ensuring human interests and development of the mahalla Decrees of the President of the Republic of Uzbekistan Investment potential of Uzbekistan Meetings Meetings The international cooperation The international cooperation Millenium development goals Millenium development goals Press-releases Press-releases Mission News Mission News The Strategy of Actions on Further Development The Strategy of Actions on Further Development Independence Day of the Republic of Uzbekistan Independence Day of the Republic of Uzbekistan Uzbekistan's Candidacy to Human Rights Council Uzbekistan’s Candidacy to Human Rights Council Tourism Tourism December 8 - Constitution Day of the Republic of Uzbekistan December 8 - Constitution Day of the Republic of Uzbekistan Press Digests of Uzbekistan Press Digests of Uzbekistan Constitutional reform Constitutional reform Other news and events Other news and events
show all useful links
RECLAMATION ACTIVITIES CONDUCT

Department of Management of the Fund of reclamation of irrigated land in the I quarter of 2015 carried out work on the enforcement of the Decree of the President of the Republic of Uzbekistan of 19 April 2013 in part to ensure a comprehensive and systematic approach of the reclamation activities, the Ministry of Finance of Uzbekistan.

During the reporting period were the construction and renovation of 149 projects, including 106 new starts and 43 passing objects.

As for the I quarter of all new objects begins design and estimate documentation and received positive conclusion of examination of 105 objects held the tenders and 101 objects defined contractors.

Work on the construction and reconstruction of reclamation projects funded in the amount of 32,25 billion. UZS. To carry out these works was drawn over 387 tools and 960 employees.

In 2015, the repair work will be carried out on 224 Priority of reclamation facilities, including 147 re-starts and 77 passing objects.

As of April 1, 2015 for all new objects start to design and estimate documentation, obtained an expert report and identified 142 objects contractors.

Today conducted repair work on 207 objects.

In the reporting period, have been mechanized cleaning of 3512,7 km. drainage network, mastered capital investments amounting to 33,3 billion UZS.

The above activities were financed in the amount of 21,74 billion. UZS. To perform these studies involved 476 excavators, 150 bulldozers and 1245 workers.

IA "Jahon"