Shavkat Mirziyoyev became familiar with construction of strategically significant Turakurgan Thermal Power Plant

SHAVKAT MIRZIYOYEV Year of ensuring human interests and development of the mahalla Year of ensuring human interests and development of the mahalla Decrees of the President of the Republic of Uzbekistan Investment potential of Uzbekistan Meetings Meetings The international cooperation The international cooperation Millenium development goals Millenium development goals Press-releases Press-releases Mission News Mission News The Strategy of Actions on Further Development The Strategy of Actions on Further Development Independence Day of the Republic of Uzbekistan Independence Day of the Republic of Uzbekistan Uzbekistan's Candidacy to Human Rights Council Uzbekistan’s Candidacy to Human Rights Council Tourism Tourism December 8 - Constitution Day of the Republic of Uzbekistan December 8 - Constitution Day of the Republic of Uzbekistan Press Digests of Uzbekistan Press Digests of Uzbekistan Constitutional reform Constitutional reform Other news and events Other news and events
show all useful links
Shavkat Mirziyoyev became familiar with construction of strategically significant Turakurgan Thermal Power Plant

On February 28, the President of the Republic of Uzbekistan Shavkat Mirziyoyev became familiar with activities carried out at Turakurgan Thermal Power Plant.

Over the years, electricity supply problems have been observed in Fergana valley. In this regard, construction of a thermal power plant based on modern technologies has begun in Turakurgan district. Commissioning of this station with a capacity of 900 MW will make it possible to fully meet the population’s and industry’s need for electricity.

The total cost of the project is more than 1 billion 195 million USD. It is funded by Japan International Cooperation Agency (JICA), the Fund for Reconstruction and Development of Uzbekistan and JSC Uzbekenergo. The station is being built by Japan’s Mitsubishi Corporation and Mitsubishi Hitachi Power Systems.

To date, the main power generating units – the first and second transformer units, combined-cycle turbine, and others have been installed. Activities on construction of external communications, water supply network have been completed. The facility will be supplied with gas through Sokh – Namangan main gas pipeline, technical water from the Grand Namangan Canal.

The first combined-cycle plant is scheduled to be commissioned in September this year, the second – in December. As a result, an additional 6.7 billion kW/hours of electricity will be generated annually for the needs of Fergana valley. 300 people will be provided with jobs.

Most importantly, the electricity produced here at cost will be cheaper than the energy generated by other TPPs.

The Head of the state was provided with information on activities implemented at the TPP, technical and economic indicators of the facility.

The President noted that this project is of great strategic importance, the station will serve to further enhance the economic potential of the region and ensure reliable electricity supply to the population.

Instructions were given on successful launch and operation of the TPP, preparation of highly qualified specialized personnel for this purpose.

www.uza.uz